(Build activities with virus restrictions)
Line 1: Line 1:
 
{{MoveMeeting}}
 
{{MoveMeeting}}
 +
 
*Meeting Time: 7:30pm-8:30pm
 
*Meeting Time: 7:30pm-8:30pm
 
*Meeting Location: Telecom (see mailing list and slack for link/number 1/2 hour before meeting time)
 
*Meeting Location: Telecom (see mailing list and slack for link/number 1/2 hour before meeting time)
 
*Floor Plan: [[File:2701InitialMoveInLayout.pdf]]
 
*Floor Plan: [[File:2701InitialMoveInLayout.pdf]]
 
*Trello Board (Schedule/Task list): https://trello.com/b/KhEDs35R/moving-hive13
 
*Trello Board (Schedule/Task list): https://trello.com/b/KhEDs35R/moving-hive13
 +
 
==Agenda==
 
==Agenda==
=== Build activities with virus restrictions===
+
===Build activities with virus restrictions===
*We can work on buildout under the "Critical Trades" exemption paragraph (paragraph k), as it supports our continued ability to provide access to tools and material for home and automotive repair (under paragraph k and paragraph h). This is not to say "we" should keep working, but that if anyone feels they want to, that they are allowed.
+
 
** All work is 100% voluntary, don't come in if you are at all hesitant
+
*We can work on buildout under the "Critical Trades" exemption paragraph (paragraph k), as it supports our continued ability to provide access to tools and material for home and automotive repair (under paragraph k and paragraph h). This is not to say that the building committee will be planning work, but that if anyone feels they want to, that they are allowed.
** Absolutely do not come in unless you are in 100% perfect health
+
**All work is 100% voluntary, don't come in if you are at all hesitant
** We must follow the required precautions
+
**Absolutely do not come in unless you are in 100% perfect health
*** Minimum size teams (4 should be enough for wall building and electrical, avoid more than 6 people in the space at all costs)
+
**We must follow the required precautions
*** Keep 6 foot distance while working
+
***Minimum size teams (4 should be enough for wall building and electrical, avoid more than 6 people in the space at all costs)
*** Have hand sanitizer available and use it regularly
+
***Wash hands
 +
***Keep 6 foot distance while working
 +
***Have hand sanitizer available
 +
***Wash hands
  
=== Floor plan===
+
===Floor plan===
* Kevin updated based on input about HVAC and comments from members, see above
+
 
* electrical circuit list/layout at 80%, need input
+
*Kevin updated based on input about HVAC and comments from members, see above
=== Wall building BOM and Material Purchase===
+
*electrical circuit list/layout at 80%, need input
* https://docs.google.com/spreadsheets/d/1WJwqHAyj9bpOAUXoCigEn_x-1Sm22IK4vo8zdtibiig/edit?usp=sharing
+
 
* ~$3,625 not including doors
+
===Wall building BOM and Material Purchase===
* Kevin has RFQs out to United, Home Depot, Lowes, Doppes, and L&W
+
 
* Kevin will be purchasing and scheduling delivery as soon as the quotes are in
+
*https://docs.google.com/spreadsheets/d/1WJwqHAyj9bpOAUXoCigEn_x-1Sm22IK4vo8zdtibiig/edit?usp=sharing
* Wall Building will require:
+
*~$3,625 not including doors
** Ramsets
+
*Kevin has RFQs out to United, Home Depot, Lowes, Doppes, and L&W
** Hammers
+
*Kevin will be purchasing and scheduling delivery as soon as the quotes are in
** Vice grip pliers/clamps
+
*Wall Building will require:
** drills with screw driving bits
+
**Ramsets
** Tin snips
+
**Hammers
** Razor Blades/box cutters
+
**Vice grip pliers/clamps
** straight edges
+
**drills with screw driving bits
** levels
+
**Tin snips
** plumb-bob
+
**Razor Blades/box cutters
** chalk line
+
**straight edges
** sawhorses
+
**levels
** ladders/scaffolding
+
**plumb-bob
 +
**chalk line
 +
**sawhorses
 +
**ladders/scaffolding
  
 
===Electrical===
 
===Electrical===
* Kevin is getting sick of doing the planning, once the circuit list is done, can someone else take it and use it to put together the list of material to get quotes and order material?
+
 
 +
*Kevin is getting sick of doing the planning, once the circuit list is done, can someone else take it and use it to put together the list of material to get quotes and order material?
  
 
==Minutes==
 
==Minutes==

Revision as of 18:42, 26 March 2020

Move Meetings
Previous: March 19th, 2020 Meeting Procedure Next: April 2nd, 2020

Agenda

Build activities with virus restrictions

  • We can work on buildout under the "Critical Trades" exemption paragraph (paragraph k), as it supports our continued ability to provide access to tools and material for home and automotive repair (under paragraph k and paragraph h). This is not to say that the building committee will be planning work, but that if anyone feels they want to, that they are allowed.
    • All work is 100% voluntary, don't come in if you are at all hesitant
    • Absolutely do not come in unless you are in 100% perfect health
    • We must follow the required precautions
      • Minimum size teams (4 should be enough for wall building and electrical, avoid more than 6 people in the space at all costs)
      • Wash hands
      • Keep 6 foot distance while working
      • Have hand sanitizer available
      • Wash hands

Floor plan

  • Kevin updated based on input about HVAC and comments from members, see above
  • electrical circuit list/layout at 80%, need input

Wall building BOM and Material Purchase

Electrical

  • Kevin is getting sick of doing the planning, once the circuit list is done, can someone else take it and use it to put together the list of material to get quotes and order material?

Minutes