==Minutes== | ==Minutes== | ||
+ | |||
+ | new pictures look amazing | ||
+ | | ||
+ | yesterday a whole bunch more walls went up | ||
+ | 60-80% framed | ||
+ | everything is plumbed | ||
+ | wash sink stubs, hot and cold water, drain and everything for the wash sink | ||
+ | craft area, too | ||
+ | dishwasher, kitchen sink | ||
+ | changed the toilet plumbing; it's copper instead of flex line | ||
+ | plumbed for the bathroom sink as well as for a mop sink, where we had the shower drawn on the sketch | ||
+ | not shaped for a shower, not sure of their intention; there's a drain and hot and cold in that corner for however we want to make use of it | ||
+ | | ||
+ | # electrical | ||
+ | 440 panel | ||
+ | 3-phase panel is up, transformer is where it's going to be | ||
+ | main panels are on the walls | ||
+ | have trunk of cable coming out of one to transformer | ||
+ | panels are not where we'd negotiated; will need to update the cable length spreadsheet | ||
+ | velzy won't be on, but we're going to need to figure out what we're going to do for subpanels | ||
+ | pictures of labels are in cable pullers, so we know what breakers we can get | ||
+ | image we want to still do sub-panel in several spots to make wiring easier | ||
+ | will need matching to what they're providing | ||
+ | | ||
+ | walking around is really awesome; it's going to be huge; shops are going to be massive | ||
+ | | ||
+ | are they hanging drywall? | ||
+ | not until we tell them to or we do it ourselves | ||
+ | not hanging until we have electrical finished | ||
+ | might want to go in ourselves and hang one side ourselves | ||
+ | then it's still accessible | ||
+ | | ||
+ | blundar doesn't mind going down and pulling cable | ||
+ | velzy reached out for quotes for electrical material | ||
+ | haven't gotten quotes yet | ||
+ | richard's is the cheapest | ||
+ | velzy did reach out to them for a quote | ||
+ | blundar gave velzy names for electricians for labor help | ||
+ | | ||
+ | we're going to want to reach out to a few electricians and get quotes to have them do some or all of the work for us | ||
+ | blundar: might want to prioritize work; like lights | ||
+ | kevin: there are lights, they don't make sense for our floor plan, so we'll need to reconfigure them but they're bright | ||
+ | | ||
+ | we need electrical material on hand | ||
+ | | ||
+ | blundar: do we have data wiring; cat5 or cat6 | ||
+ | drew: i need to work with Kevin this week or next to hammer out the lengths we need; i have some developments | ||
+ | i talked to 2701's IT this week; some things have changed | ||
+ | blundar: i have 600-800 foot of CAT5E or CAT6 from projects | ||
+ | i have a decent number of light switches and outlets; our house is wired at this point, won't use it | ||
+ | i'll take inventory and bring it down | ||
+ | kevin: we've got a good count of what we'll need, so if you let us know what you have we can use it | ||
+ | blundar: i'll try to get it done over the weekend | ||
+ | kevin: quotes this week to decide who we're going with | ||
+ | blundar: it might make sense to get some supplies ASAP; as soon as walls are up if electric prevents the drywall going up we should get started on it | ||
+ | kevin: first thing the subpanels need to go in. velzy's RFQ didn't include subpanels | ||
+ | blundar: could start with the bathroom | ||
+ | kevin: bathroom circuits are planned out; it's framed and plumbed and ready for electrical | ||
+ | blundar: i have 30-100 feet of 12-2 or 14-2 laying around; | ||
+ | kevin: that's only so helpful; most of our runs are around 100' | ||
+ | bring it in | ||
+ | we were planning on doing everything in MC | ||
+ | blundar: no | ||
+ | kevin: we'll pass | ||
+ | recepticles and switches we can make use of | ||
+ | | ||
+ | kevin: landlord is covering wall build out | ||
+ | blundar: what's his poison? | ||
+ | kevin: rent checks | ||
+ | blundar: poison never hurts | ||
+ | kevin: he wants to hang out when we have a party | ||
+ | lisa: invite him when we have our open party | ||
+ | | ||
+ | kevin: shower drain? | ||
+ | plumber quoted $2500 to bore through the floor and have a shower drain | ||
+ | didn't budget that | ||
+ | can be added later | ||
+ | i think we should do it later | ||
+ | schwinn: there's a shower on the first floor | ||
+ | blundar: that's kind of a bonus; and having access on the first floor | ||
+ | schwinn: $2500 is almost the whole kitchen budget | ||
+ | to throw a hole in the floor | ||
+ | drew: we can keep it clear and add it later | ||
+ | kevin: can put a mop sink in and pull it out later | ||
+ | schwinn: is there going to be a mop sink outside? | ||
+ | kevin: a mess sink; like a utility sink | ||
+ | schwinn: i'm cold on it | ||
+ | blundar: if we can postpone, that's adequate | ||
+ | chris: a 6" diamond drill is $40 a day to rent | ||
+ | the drill itself is $150-160 a day | ||
+ | if we wanted to fuck around with doing it, for $500 we could drill the hole easily | ||
+ | we could do that if we wanted to mess with it | ||
+ | doesn't have to happen now | ||
+ | tim: punt! punt! punt! punt! | ||
+ | | ||
+ | kevin: we'll have other things to put up for vote | ||
+ | | ||
+ | kevin: kitchen? | ||
+ | it's ready for stuff to start buying there | ||
+ | if you find something to get, that needs to happen now | ||
+ | schwinn: my additude about the urgency of it being open when we open has shifted; it might be a while before we need it | ||
+ | blundar: having a refigeration unit, and sink, and something to generate heat would be nice | ||
+ | | ||
+ | kevin: we're taking the stove and fridge from here | ||
+ | schwinn: it might not be spit-polished by then | ||
+ | we'd talked about the kitchen being there on day one | ||
+ | i've abandoned that notion | ||
+ | i don't know what day 1 actually is | ||
+ | | ||
+ | kevin: we have to just go with the flow on how this goes | ||
+ | schwinn: it's cool that we have other people to do this ourselves | ||
+ | we can figure out how to do the rest safely on our own terms | ||
+ | | ||
+ | kevin: i'm still worried about the electrical in that respect | ||
+ | schwinn: yeah, but you're not going to be thinking about the walls | ||
+ | you were really strung out 2 months ago about who's doing what when | ||
+ | now it's answered itself | ||
+ | | ||
+ | burdick: i like that we can keep social distancing in our new space; functional work space | ||
+ | chris: one thing i'm looking at is that the more outside and fresh air the better | ||
+ | i'm pushing to basically not open for customers indoors since we own a parking lot and patio | ||
+ | the more that we can open windows, the better | ||
+ | the less that we're recycling through HVAC, the better | ||
+ | | ||
+ | dust collection blowing out the side of the building; and ventilation doing that would probably be an ASAP priority | ||
+ | | ||
+ | schwinn: i'll look into windows | ||
+ | kevin: 2701 will install windows | ||
+ | | ||
+ | drew: we had a chat with 2701's it person (velzy and drew) | ||
+ | they are prepared to provide internet, firewall, and wireless, and an ethernet handoff to anything we want | ||
+ | my BOM got shorter by not needing to buy a router | ||
+ | he's going to allow incoming VPN, azure connections, etc. | ||
+ | | ||
+ | he uses new access points; he'll be covering the space with wireless APs | ||
+ | he's going to give each tenant a vlan and independent firewall rules | ||
+ | thanks to some of us lifting some of our infrastructure into the cloud, we can bring that in easily | ||
+ | | ||
+ | chris: what's the bandwidth coming into the building? | ||
+ | drew: it's through CBTS; it's not fioptics | ||
+ | metro ethernet | ||
+ | | ||
+ | kevin: what do we want to do ourselves? | ||
+ | what are we taking over to the building? | ||
+ | | ||
+ | blundar and kevin bringing big table over and leaving blundar's truck there | ||
+ | lisa: if you take a table, take 2 chairs or stools or something? | ||
+ | schwinn: i second that | ||
+ | | ||
+ | schwinn: my agenda doesn't interfere; i'm going to clean windows and build sound baffles which hang from the ceiling | ||
+ | chris: speaking of the big tables; | ||
+ | is that cart still there with all the chairs? we can take that cart and one or two tables from the lounge | ||
+ | | ||
+ | kevin: i'm also interested in taking a couch and recliner for the new lounge | ||
+ | we can start building out a cmofy spot | ||
+ | | ||
+ | schwinn: when will we have access to wifi? | ||
+ | drew: he'll let me know when they come in; we'd have an ethernet handoff for our switches and APs | ||
+ | | ||
+ | schwinn: my work does not care if i cowork; my work from home brings a lot of liberty; as soon as i have my laptop set up there i can work from there | ||
+ | drew: i'll have him add a configuration for us and pass that along | ||
+ | | ||
+ | jill: i can help cleaning windows | ||
+ | schwinn: there's like 18 of them | ||
+ | jill: since i'm not doing school, i can't stand being in the house all day | ||
+ | schwinn: i'll take the screens out for pressure washing | ||
+ | | ||
+ | kevin: if you have a list of things to move over post it in slack | ||
+ | wall builders won't be doing any more work until tuesday | ||
+ | | ||
+ | drew: can we get together to set up for ethernet runs? | ||
+ | | ||
+ | schwinn: sounds like we're moving the hive | ||
+ | blundar: it's real! | ||
+ | | ||
+ | drew: i'll have to give you locations and switch stacks and drops | ||
+ | kevin: that's what i did with the sub panels for the electric |
Revision as of 08:44, 22 May 2020
Move Meetings | ||
---|---|---|
Previous: May 14th, 2020 | Meeting Procedure | Next: May 28th, 2020 |
- Meeting Time: 7:30pm-8:30pm
- Meeting Location: Telecom
- To join the video meeting, click this link: https://meet.google.com/nny-rnee-yyt
- Otherwise, to join by phone, dial +1 501-939-4183 and enter this PIN: 954 248 025#
- To view more phone numbers, click this link: https://tel.meet/nny-rnee-yyt?hs=5
- Floor Plan: File:2701InitialMoveInLayout.pdf
- Trello Board (Schedule/Task list): https://trello.com/b/KhEDs35R/moving-hive13
Agenda
Build Progress
- Material Delivered
- Bathroom/kitchen Framed
- Landlord is covering wall build labor to compensate for delays
- Shower drain
- Would cost about $2500 as it needs to core drill through to the floor below.
- There is a shower on the first floor that we can use
- Should we have the drain installed or use the shower on the 1st?
What's Next?
- Need to take our tools over?
- What work do we want to do ourselves?
Minutes
new pictures look amazing yesterday a whole bunch more walls went up 60-80% framed everything is plumbed wash sink stubs, hot and cold water, drain and everything for the wash sink craft area, too dishwasher, kitchen sink changed the toilet plumbing; it's copper instead of flex line plumbed for the bathroom sink as well as for a mop sink, where we had the shower drawn on the sketch not shaped for a shower, not sure of their intention; there's a drain and hot and cold in that corner for however we want to make use of it
- electrical
440 panel 3-phase panel is up, transformer is where it's going to be main panels are on the walls have trunk of cable coming out of one to transformer panels are not where we'd negotiated; will need to update the cable length spreadsheet velzy won't be on, but we're going to need to figure out what we're going to do for subpanels pictures of labels are in cable pullers, so we know what breakers we can get image we want to still do sub-panel in several spots to make wiring easier will need matching to what they're providing walking around is really awesome; it's going to be huge; shops are going to be massive are they hanging drywall? not until we tell them to or we do it ourselves not hanging until we have electrical finished might want to go in ourselves and hang one side ourselves then it's still accessible blundar doesn't mind going down and pulling cable velzy reached out for quotes for electrical material haven't gotten quotes yet richard's is the cheapest velzy did reach out to them for a quote blundar gave velzy names for electricians for labor help we're going to want to reach out to a few electricians and get quotes to have them do some or all of the work for us blundar: might want to prioritize work; like lights kevin: there are lights, they don't make sense for our floor plan, so we'll need to reconfigure them but they're bright we need electrical material on hand blundar: do we have data wiring; cat5 or cat6 drew: i need to work with Kevin this week or next to hammer out the lengths we need; i have some developments i talked to 2701's IT this week; some things have changed blundar: i have 600-800 foot of CAT5E or CAT6 from projects i have a decent number of light switches and outlets; our house is wired at this point, won't use it i'll take inventory and bring it down kevin: we've got a good count of what we'll need, so if you let us know what you have we can use it blundar: i'll try to get it done over the weekend kevin: quotes this week to decide who we're going with blundar: it might make sense to get some supplies ASAP; as soon as walls are up if electric prevents the drywall going up we should get started on it kevin: first thing the subpanels need to go in. velzy's RFQ didn't include subpanels blundar: could start with the bathroom kevin: bathroom circuits are planned out; it's framed and plumbed and ready for electrical blundar: i have 30-100 feet of 12-2 or 14-2 laying around; kevin: that's only so helpful; most of our runs are around 100'
bring it in we were planning on doing everything in MC
blundar: no kevin: we'll pass
recepticles and switches we can make use of
kevin: landlord is covering wall build out blundar: what's his poison? kevin: rent checks blundar: poison never hurts kevin: he wants to hang out when we have a party lisa: invite him when we have our open party kevin: shower drain?
plumber quoted $2500 to bore through the floor and have a shower drain didn't budget that can be added later i think we should do it later
schwinn: there's a shower on the first floor blundar: that's kind of a bonus; and having access on the first floor schwinn: $2500 is almost the whole kitchen budget
to throw a hole in the floor
drew: we can keep it clear and add it later kevin: can put a mop sink in and pull it out later schwinn: is there going to be a mop sink outside? kevin: a mess sink; like a utility sink schwinn: i'm cold on it blundar: if we can postpone, that's adequate chris: a 6" diamond drill is $40 a day to rent
the drill itself is $150-160 a day if we wanted to fuck around with doing it, for $500 we could drill the hole easily we could do that if we wanted to mess with it doesn't have to happen now
tim: punt! punt! punt! punt! kevin: we'll have other things to put up for vote kevin: kitchen?
it's ready for stuff to start buying there if you find something to get, that needs to happen now
schwinn: my additude about the urgency of it being open when we open has shifted; it might be a while before we need it blundar: having a refigeration unit, and sink, and something to generate heat would be nice kevin: we're taking the stove and fridge from here schwinn: it might not be spit-polished by then
we'd talked about the kitchen being there on day one i've abandoned that notion i don't know what day 1 actually is
kevin: we have to just go with the flow on how this goes schwinn: it's cool that we have other people to do this ourselves
we can figure out how to do the rest safely on our own terms
kevin: i'm still worried about the electrical in that respect schwinn: yeah, but you're not going to be thinking about the walls
you were really strung out 2 months ago about who's doing what when now it's answered itself
burdick: i like that we can keep social distancing in our new space; functional work space chris: one thing i'm looking at is that the more outside and fresh air the better
i'm pushing to basically not open for customers indoors since we own a parking lot and patio the more that we can open windows, the better the less that we're recycling through HVAC, the better
dust collection blowing out the side of the building; and ventilation doing that would probably be an ASAP priority
schwinn: i'll look into windows kevin: 2701 will install windows drew: we had a chat with 2701's it person (velzy and drew)
they are prepared to provide internet, firewall, and wireless, and an ethernet handoff to anything we want my BOM got shorter by not needing to buy a router he's going to allow incoming VPN, azure connections, etc.
he uses new access points; he'll be covering the space with wireless APs he's going to give each tenant a vlan and independent firewall rules thanks to some of us lifting some of our infrastructure into the cloud, we can bring that in easily
chris: what's the bandwidth coming into the building? drew: it's through CBTS; it's not fioptics
metro ethernet
kevin: what do we want to do ourselves?
what are we taking over to the building?
blundar and kevin bringing big table over and leaving blundar's truck there lisa: if you take a table, take 2 chairs or stools or something? schwinn: i second that schwinn: my agenda doesn't interfere; i'm going to clean windows and build sound baffles which hang from the ceiling chris: speaking of the big tables;
is that cart still there with all the chairs? we can take that cart and one or two tables from the lounge
kevin: i'm also interested in taking a couch and recliner for the new lounge
we can start building out a cmofy spot
schwinn: when will we have access to wifi? drew: he'll let me know when they come in; we'd have an ethernet handoff for our switches and APs schwinn: my work does not care if i cowork; my work from home brings a lot of liberty; as soon as i have my laptop set up there i can work from there drew: i'll have him add a configuration for us and pass that along jill: i can help cleaning windows schwinn: there's like 18 of them jill: since i'm not doing school, i can't stand being in the house all day schwinn: i'll take the screens out for pressure washing kevin: if you have a list of things to move over post it in slack
wall builders won't be doing any more work until tuesday
drew: can we get together to set up for ethernet runs? schwinn: sounds like we're moving the hive blundar: it's real! drew: i'll have to give you locations and switch stacks and drops kevin: that's what i did with the sub panels for the electric